MGEN Trois-Épis: Hospital Hot Water Scale Free for 5 Years

Home 9 Case Studies and Results 9 MGEN Trois-Épis: Hospital Hot Water Scale Free for 5 Years
Key results
5 years scale-free
Zero pipe blockages
95% lower OPEX

Case Study from HydroFLOW France

Hospital hot water scale on very hard Colmar water

Hospital hot water scale is a constant pressure at the 206-bed MGEN Trois-Épis rehabilitation centre in Alsace, where domestic hot water is produced from very hard Colmar water at approximately 330 ppm. The site relied on six ageing salt softeners whose resins needed replacing and whose regeneration consumed significant salt and water. It also saw a few Legionella alerts on its hot water network each year. Twelve HydroFLOW® units replaced the softeners across 2,550 kW of hot water production, installed in a single day without interrupting water service. Five years on, no limescale-related maintenance has been needed, Dalkia has recorded no callouts for scale-blocked pipes, and a dismantled plate exchanger showed no trace of limescale.

The Challenge

  • Hospital hot water scale control depended on six ageing salt softeners
  • Very hard Colmar water at approximately 330 ppm fed the domestic hot water system
  • Softener regeneration consumed significant salt and water
  • Ageing softener resins were due for replacement
  • A few Legionella alerts occurred on the hot water network each year

The Solution

  • Units installed: twelve HydroFLOW® units
  • Installation point: main substation, four exchangers, a villa boiler and three villa tanks
  • Water: very hard Colmar supply, approximately 330 ppm
  • Previous treatment: six salt softeners
  • Monitoring period: five years of maintenance contractor records

All twelve units were fitted in one day without interrupting water service, covering the main substation, the 300 kW Roseraie exchanger, the 200 kW Leisure and Balneo exchangers, a villa boiler and the tanks in three villas. With the softeners removed, hospital hot water scale control now comes from the signal alone, so there is no salt, no regeneration water and no resin to replace.

Key Outcomes

R

No limescale maintenance in five years

R

Operating cost €50 vs €1,250 per 1,000 m³

R

Zero scale-related DHW pipe blockages

R

Plate exchanger free of limescale at five years

Independent Verification

All results in this study were measured and verified by third-party facilities managers and technical staff.

Summary

Five years after the softeners were removed, the site has needed no limescale-related maintenance and has had no Legionella alert on the hot water network. The source comparison calculated upfront equipment cost at around €2,500 for HydroFLOW® against €5,000 for replacing the softeners, and annual operating cost at €50 against €1,250 for every 1,000 m³ of water produced. Five years of records from the site's own maintenance contractor are what make those figures worth quoting.

Ready to see more?

Ready to explore sustainable water treatment?

Get in touch to find out how HydroFLOW® can work for you.

© 2026 Hydropath Technology Ltd. All rights reserved