Poland Moulding: Softeners Removed, Cycle Time Cut

Home 9 Case Studies and Results 9 Poland Moulding: Softeners Removed, Cycle Time Cut
Key results
0 water softener use
Improved cycle time
1 month cleaning interval

Case Study from Hydropath Poland

The Challenges

  • Scale and biofilm in cooling channels
  • Rotometers requiring monthly cleaning
  • Reduced heat transfer affecting cycle time
  • Increased operating costs

The Solution

Two HydroFLOW® P120 units and one S38 unit were fitted to cooling circuits and the heat exchanger in July 2017, on 114mm and 30mm pipe. The signal disrupts the conditions that bond scale and biofilm to surfaces, letting the ion exchange softeners be removed.

Key Outcomes

R

Scale and biofilm reduced across the system

R

Improved heat transfer and cooling

R

Ion exchange softeners disconnected

R

Injection moulding cycle time reduced

Independent Verification

All results in this study were measured and verified by third-party facilities managers and technical staff.

Ready to see more?