Case Study from HYDROPATH Asia
Retail portfolio cooling water treatment across 100+ units
Retail portfolio cooling water systems across a Hong Kong commercial property group’s malls relied on chemical dosing and annual condenser cleaning, with scale build-up in the condenser tubes affecting chiller performance and bleed-off needed to control conductivity. In 2013 HydroFLOW® units were piloted on the cooling water systems at the group’s flagship mall. The condenser tubes were left uncleaned before installation. After 12 months the remaining scale was completely gone, and tube cleaning shifted from annual to on-demand. The successful pilot at the flagship mall led to a full rollout across multiple properties, with more than 100 units installed across more than 50 shopping malls.
The Challenges
- Retail portfolio cooling water systems had scale build-up in condenser tubes, affecting chiller performance
- Annual condenser tube cleaning was required at each mall
- Continuous chemical dosing was in use across the portfolio
- Bleed-off was needed to control conductivity between 1,500 and 1,200 µS/cm
The Solution
- Units installed: more than 100 HydroFLOW® units across the portfolio
- Installation point: cooling water systems, starting at the flagship mall
- Installed: 2013 pilot, then rollout across the portfolio
- Trial: pilot on uncleaned condenser tubes, scale gone within 12 months
The pilot started in 2013 at the flagship mall, with the condenser tubes left uncleaned before installation. After 12 months of HydroFLOW® operation the remaining scale was completely gone, and chiller performance was maintained without the need for frequent manual cleaning. The successful pilot led to a full rollout of the retail portfolio cooling water programme across multiple properties.