Orlando Belt Press: Pan Scale 5 mm to 1 mm in 150 Days

Home 9 Case Studies and Results 9 Orlando Belt Press: Pan Scale 5 mm to 1 mm in 150 Days
Key results
20% lower daily polymer use
Pan scale 5 mm down to 1 mm
150 days with no cleaning

Case Study from HydroFLOW USA

The Challenge

  • Belt press pan scale had reached around 5 mm of hard struvite
  • Hard scale bridged the holes in the press drum
  • Polymer dosing and cleaning frequency were both under review
  • Cleaning required belt removal and hot water
  • Centrate was transferred continuously, 24 hours a day

The Solution

One HydroFLOW® Custom 12 inch unit was installed on the belt press influent pipe, downstream of anionic polymer injection, and run continuously for 150 days on an AshBrook Klam press with two 2 metre wide belts. New struvite accumulation was controlled and existing deposits softened, with pan scale falling from 5 mm to 1 mm of brittle scale. Flocculation improved enough to cut average daily polymer use by about 20%, and the press ran the full 150 days without a scale clean.

Testimonial

“After 10 days of use, there was a marked reduction in the amount of struvite buildup and eventually the struvite had softened to the point that it could be wiped off by hand. During the demonstration, the unit was run continuously without any cleaning.” — Steve Shelnutt, Plant Manager, Water Conserv II

Key Outcomes

R

Average daily polymer use fell by approximately 20%

R

The belt press ran 150 days continuously without scale cleaning

R

Hard pan scale reduced from 5 mm to 1 mm of brittle scale

R

Minimal new struvite remained on the drum after 150 days

Independent Verification

All results in this study were measured and verified by third-party facilities managers and technical staff.

Ready to see more?

Ready to explore sustainable water treatment?

Get in touch to find out how HydroFLOW® can work for you.

© 2026 Hydropath Technology Ltd. All rights reserved