Key results
75% biocide reduction
65% blowdown reduction
<2 year payback period

Summary

Biocide use fell by 75% while CFU levels were kept below 1,000, and blowdown fell by over 65%. Conductivity was raised from about 1,400 to 4,000 µS without signs of fouling, scale chemicals were discontinued four months after installation, and the maintenance team reported the cleanest chiller tubes they had observed.

Case Study from HydroFLOW USA

Cooling tower biocide reduction at a hospital cooling plant

Cooling tower biocide reduction was needed at a California hospital that held conductivity at about 1,400 µS to limit fouling and relied on high chemical dosing to control biofilm and scale. HydroFLOW® Custom units were fitted to the condenser return lines and chillers, alongside side stream and glass bead media filtration, and the system was monitored over seven months. The system ran at up to 4,000 µS without signs of fouling; biocide use fell by 75% and blowdown by over 65%, and the maintenance team reported the cleanest chiller tubes they had observed.

The Challenges

  • Cooling tower biocide reduction was needed alongside lower antiscalant dosing
  • Conductivity was limited to about 1,400 µS due to fouling risk
  • High chemical dosing was required for control
  • Biofilm and scale formation were a risk
  • Deposits risked reducing cooling efficiency

The Solution

  • Units installed: HydroFLOW® Custom units
  • Installation point: condenser return lines and chillers
  • Monitoring period: over seven months
  • Previous treatment: heavy biocide and antiscalant dosing at low conductivity

The units were fitted to the condenser return lines and chillers, with side stream and glass bead media filtration. Conductivity was raised from about 1,400 to 4,000 µS without signs of fouling. Cooling tower biocide reduction reached 75% while CFU levels were kept below 1,000, blowdown fell by over 65%, and anti-scalant and anti-corrosive chemicals were discontinued four months after installation.

Key Outcomes

R

Biocide use reduced by 75%, CFU below 1,000

R

Scale chemicals stopped 4 months after install

R

Blowdown water reduced by over 65%

R

Cleanest chiller tubes the team had recorded

Independent Verification

All results in this study were measured and verified by third-party facilities managers and technical staff.