Mine pipeline occlusion on pulp hydrotransport lines
Mine pipeline occlusion could block two pulp hydrotransport pipelines at the Norilsk mine within a month and a half. The lines, 219 to 245 mm in diameter, ran at 60 to 70°C. Deposits grew faster when pulp density exceeded 1.3, reached up to 200 mm thick and cut carrying capacity badly enough to disrupt production. On 30 March 2012 two HydroFLOW® Custom 12 inch units were installed on the two lines without stopping the system. Occlusion fell by a factor of 8.8 and the volume pumped rose 2.26 times as lime and gypsum deposition slowed.
The Challenge
- Mine pipeline occlusion could block the lines within 1.5 months
- Deposits built up faster when pulp density exceeded 1.3
- Deposit thickness reached up to 200 mm
- Reduced carrying capacity disrupted production
- The lines ran hot, at 60 to 70°C
- The lines could not be stopped for the installation
The Solution
- Unit installed: two HydroFLOW® Custom 12 inch units
- Installation point: two pulp hydrotransport pipelines, fitted without stopping the lines
- Pipe size: 219 to 245 mm diameter
- Installed: 30 March 2012
Because the hydrotransport system could not be stopped, both units were fitted to the live lines. The signal disrupts the conditions that bond scale to surfaces, so lime and gypsum deposition slows and pipeline carrying capacity is maintained. Mine pipeline occlusion and the volume pumped were then measured on the two treated lines.