Cooling tower bio-count reduction at a US Southeast office complex
Cooling tower bio-count reduction was needed at a complex with 2.3 million square feet across six office buildings, more than 50 restaurants and shops and three hotels, without compromising a water-saving strategy that ran the towers at high cycles of concentration. Bio-counts had reached around 100,000 CFU against a target below 10,000, and scale and biofilm were affecting the cooling tower and chiller surfaces. One HydroFLOW® Custom 14 inch unit was installed on the south-tower cooling and chiller system for a planned 90 day trial. Within days bio-counts fell below 1,000 CFU and scale and biofilm reduced. The trial led to the unit being bought outright, and further units followed across the complex.
The Challenge
- Cooling tower bio-count reduction was needed without giving up the site’s water-saving strategy
- Bio-counts had reached approximately 100,000 CFU
- The required target was below 10,000 CFU
- High cycles of concentration cut water use but caused severe scale and biological fouling
- Scale and biofilm affected both cooling tower and chiller surfaces
The Solution
- Unit installed: one HydroFLOW® Custom 14 inch
- Installation point: south-tower cooling and chiller water system
- Trial: 90 days planned, leading to the unit being purchased outright
Cooling tower bio-count reduction was measured against the site’s own 10,000 CFU target, and the aim was better biological control without compromising the site’s water-saving strategy. The unit went on the south tower’s cooling and chiller water system, and reduced scale was later reported in both the tower and the chiller tubes. Bio-counts were followed from the start of the planned 90 day trial and moved within days.