Hong Kong Seawater Chillers: COP Up 10-15%, Biofilm Removed

Home 9 Case Studies and Results 9 Hong Kong Seawater Chillers: COP Up 10-15%, Biofilm Removed
Key results
10-15% COP improvement
2 months to remove biofilm
5 buildings treated

Case Study from HYDROPATH Asia

Seawater cooled chiller biofilm across five buildings

Seawater cooled chiller biofilm remained on the condenser tubes of five Hong Kong commercial buildings, even though all of them ran electro-chlorination and automatic tube cleaning. Hong Kong limits chlorine discharge to 0.2 ppm, so chlorination could not simply be turned up, and annual tube cleaning was the fallback. HydroFLOW® treatment was installed at an initial trial building and then rolled out to four more. The biofilm cleared within two months and chiller COP improved by 10 to 15%, with chlorine discharge staying within the 0.2 ppm limit. The same approach was repeated at each of the four further buildings with consistent results.

The Challenges

  • Seawater cooled chiller biofilm remained on condenser tubes despite chlorination
  • Annual tube cleaning was required at every building
  • Electro-chlorination and automatic tube cleaning were both still in use
  • Chlorine discharge was limited to 0.2 ppm, capping the chemical route
  • Fouled tubes were holding chiller COP down

The Solution

  • Installation point: seawater-cooled chiller plant, one trial building then four more
  • Previous treatment: electro-chlorination and automatic tube cleaning
  • Water: seawater, with chlorine discharge limited to 0.2 ppm

HydroFLOW® treatment went in at one trial building first, then at four more. The signal disrupts the conditions that let biofilm establish on condenser tubes, so seawater cooled chiller biofilm cleared within two months. Chiller COP rose by 10 to 15% as heat transfer recovered, and the buildings stayed within the 0.2 ppm chlorine discharge limit throughout.

Key Outcomes

R

Condenser tubes free of biofilm in two months

R

Automatic Tube Cleaning System shut down

R

14-month log showed COP up 10-15%

R

Worked within the 0.2 ppm chlorine limit

Independent Verification

All results in this study were measured and verified by third-party facilities managers and technical staff.

Summary

Condenser tube biofilm cleared within two months and chiller COP rose by 10 to 15%, without breaching the 0.2 ppm chlorine discharge limit. Where chlorine discharge is capped by regulation, as it is in Hong Kong, the chemical route runs out of headroom. This case study shows the alternative holding across five buildings within the same limit.

Ready to see more?

Ready to explore sustainable water treatment?

Get in touch to find out how HydroFLOW® can work for you.

© 2026 Hydropath Technology Ltd. All rights reserved